View the Late Night Work      (updated weekly)

Project Description

Work Schedule

Container Gardening Tips


Proposed Schedule for Squirrel Hill Tunnel Project

November 7 - 15 Irrigation trenches and asphalt leveling pads installed on
the suburban side

November 17 - December 7 Concrete planters placed in planters on suburban side and city side entrances. Trees, shrubs and bulbs planted.

Scheduled work times are Sunday through Thursday, 10:00 p.m. - 6:00 a.m., starting November 10, 2002. Dates are subject to change.

 